The unstable hill above the house had loose soil that could slide away at any time, endangering the house and the inhabitants. The Santa Cruz County Environmental Department required hillside repair before anyone was allowed to move in.

We removed 60 cubic yards of hillside soil and installed grouted anchors 15 feet into the hillside and installed a structural chain link fence and Tecco mesh fence.

This process ties the hillside together to stop further soil erosion and keep the structure safe. The environmental planning department of the county returned to inspect the project and gave the project their approval.